Project Status
May 2008
On May 2nd crews set the 9th of 32 girders for the new I-405 southbound bridge over I-90.
Night closures on I-90, I-405: Starting April 29 through early May, crews will set bridge girders for the new southbound bridge over I-90. This work will be done in phases and, requires a series of weeknight closures of lanes and ramps on I-405 and I-90. Crews to remove Wilburton Tunnel in 2008. This project has been selected as Quieter Pavement test section.
May 2008
On May 2nd crews set the 9th of 32 girders for the new I-405 southbound bridge over I-90.
Night closures on I-90, I-405: Starting April 29 through early May, crews will set bridge girders for the new southbound bridge over I-90. This work will be done in phases and, requires a series of weeknight closures of lanes and ramps on I-405 and I-90. Crews to remove Wilburton Tunnel in 2008. This project has been selected as Quieter Pavement test section.
Existing I-405/I-90 Interchange
The I-405/I-90 Interchange after completion of the South Bellevue Widening project. Improvements include a new southbound bridge over I-90 and a northbound bridge over Coal Creek Parkway.
No comments:
Post a Comment